‘A Monstrous Monument to Greed and Stupidity’: Critics React to Site C Decision

‘A Monstrous Monument to Greed and Stupidity’: Critics React to Site C Decision

BC Liberals accuse NDP of mismanagement; Greens warn public to brace for higher costs.

Premier John Horgan’s announcement today that the government will continue with the Site C dam despite massive budget increases and delays brought criticism from opponents and supporters of the project.

“We’ve seen mismanagement of this file,” said Tom Shypitka, the BC Liberal critic for energy, mines and low carbon innovation. “It’s a sad day for the taxpayers, but it’s a good thing to see Site C proceed for the future of British Columbians.”

Horgan announced the government will continue with the project even though the budget has grown to $16 billion, an increase he blamed largely on unexpected geotechnical issues and delays due to the COVID-19 pandemic. It is now expected to be in service in 2025.

The Site C budget was $7.9 billion in 2010. When the NDP decided to continue construction in 2017 they increased the budget to $10.7 billion.

Shypitka said the cost of the dam has doubled since the NDP came to government and that the oversight committee it put in place in 2018 has clearly failed. “Under their watch, this project has gone off the rails. That’s on the NDP government.”

He rejected the idea the BC Liberals should have been more diligent before starting the project. It’s unclear how much of the delay and cost escalation can be blamed on the pandemic and how much was due to the NDP’s mismanagement, he said.

…click on the above link to read the rest of the article…

 

Why Site C Construction Should Stop Today

Why Site C Construction Should Stop Today

The BC government has failed in its oversight role, say a former BC Hydro CEO and a veteran dam engineer.

Site C is the most expensive publicly funded infrastructure project in British Columbia’s history and the dam’s construction is being spearheaded by BC Hydro, a publicly owned hydroelectric utility whose sole shareholder is the provincial government.

That ought to mean that our elected leaders and civil servants place the highest priority on keeping on top of everything that goes on at Site C, because ultimately all British Columbians must pay for the project.

But there is an even more compelling reason why our government must be fully and effectively engaged on this project. All dams built in British Columbia must, by provincial statute, be designed, built and maintained to the highest safety standards.

Dams do not fail often. But when they do, the losses can be devastating. Which is why B.C.’s dam safety regulation is in place, and why it falls to engineers and dam safety officials employed by the provincial government to ensure that all dams built in the province have structural integrity.

Unfortunately, this important responsibility has rarely been mentioned as Site C has careened from one set of problems to another.

First there was the troubling tension crack that opened a gaping maw on the north riverbank following initial excavation work in 2017, leading to the removal of millions of cubic metres of additional earth to stabilize a clearly unstable bank.

Then there was problem after problem drilling the project’s diversion and drainage tunnels, as portions of the concrete liners anchored to the tunnel walls gave way and crashed to the tunnel floors — incidents later attributed to the soft shale that dominates the site.

…click on the above link to read the rest of the article…

Horgan Seems Fine with Muzzling the True Site C Watchdog

Horgan Seems Fine with Muzzling the True Site C Watchdog

The independent BC Utilities Commission demanded answers on risks and was brushed off.

BC Hydro has, in a Trumpian gesture, brushed off the last independent oversight of the out-of-control Site C project, with the apparent support of the newly elected NDP government.

The BC Utilities Commission is supposed to make sure BC Hydro is acting responsibly in the interests of its customers. It’s the only check on the monopoly $6-billion Crown corporation.

But BC Hydro just gave the finger to the regulator, and to British Columbians. And Premier John Horgan seems to be fine with that.

The utilities commission is mandated to ensure BC Hydro makes good decisions in the public interest. It scrutinizes the corporation’s budgets, plans and projections. It approves — or rejects — rate increases, and reports on whether projects like Site C are needed and based on a sound business case.

In doing that, it relies on BC Hydro to accept the oversight and provide needed information.

And BC Hydro has simply dismissed its obligation to accept independent oversight.

On July 31, BC Hydro filed updates on Site C with the utilities commission.

They were alarming. BC Hydro revealed there was “uncertainty with the dam’s schedule and in-service date” and “significant financial pressures.” So significant the corporation said it was coming up with a new budget and schedule for the megaproject.

And BC Hydro said that in late December a “project risk” had “materialized.”

The dam’s main structures — spillways and the giant power generating hall — are being built on unstable ground. The corporation is trying to figure out a solution and it has no idea how much this will cost.

…click on the above link to read the rest of the article…

‘No Need for Site C’: Review Panel Chair Speaks Out Against Dam in New Video

‘No Need for Site C’: Review Panel Chair Speaks Out Against Dam in New Video

I think we’re making a big mistake, a very expensive one,” Swain says in the video. “Of the $9 billion it will cost, at least $7 billion will never be returned. You and I as rate payers will end up paying $7 billion bucks for something we get nothing for.”

Since 2005, domestic demand for electricity in B.C. has been essentially flat, making it difficult to justify the dam which will flood 107 kilometres of the Peace River and destroy thousands of hectares of prime agricultural land.

There is no need for Site C,” Swain says. “If there was a need, we could meet it with a variety of other renewable and smaller scale sources.”

With a price tag of $8.8 billion, Site C dam is the most expensive public infrastructure project in B.C.’s history. The joint review panel that Swain chaired found demand for the power had not been proven and called for the project to be reviewed by the B.C. Utilities Commission — a recommendation the B.C. government ignored.

Swain first spoke out about the Site C dam last year, but this is the first video interview on the subject with the former deputy minister of Indian and Northern Affairs.

The provinces have the responsibility for the management of natural resources. I don’t think British Columbia has done its job,” Swain says, referring to B.C.’s failure to investigate alternatives to the Site C dam.

Swain outlined the economic case against the dam in an opinion piece in the Vancouver Sun on Friday.

 

…click on the above link to read the rest of the article…

As Site C Breaks Ground, Linked Union Declares Opposition

As Site C Breaks Ground, Linked Union Declares Opposition

BCGEU cites First Nation infringement and loss of habitat in motion against controversial dam.

The union representing many British Columbia government workers has taken a position against building the Site C dam, a project some of its members are working on and that other unions support.

“This was a membership driven motion,” said Stephanie Smith, the president of the B.C. Government and Service Employees’ Union. “We have 68,000 members and there is a diversity of interests.”

Smith said the motion was brought forward by the union’s environment committee and passed unanimously. There was no debate even though Smith invited discussion, she said.

A statement from the union said it opposes building the dam because it is not needed, it will cause a loss of habitat, it infringes First Nations’ hunting and fishing rights, productive agricultural lands will be lost and it fails the economic test of “providing a lasting net benefit to British Columbians.”

First proposed some 30 years ago, Site C is to be the third of a series of dams on the Peace River and will flood an 83-kilometre long stretch of the river to generate 1,100 megawatt hours of electricity, enough to power 450,000 homes per year.

The provincial government approved the $8.8-billion BC Hydro project in Dec. 2014 and announced it intended to start construction this summer.

BC Hydro spokesperson Kevin Aquino confirmed project construction has begun, and will ramp up over the summer. ”Security has mobilized to [the] site and some initial clearing activities on the north bank of the dam site area are underway,” he said, adding gates and signage have been installed.

Several First Nations and local landowners have filed lawsuits trying to stop BC Hydro from building the dam.

Publicly owned asset

BCGEU members have been involved in the planning and approval of the project. Within B.C.’s energy and mines ministry, about half a dozen members are currently working on the Site C file, a ministry spokesperson confirmed.

 

…click on the above link to read the rest of the article…

 

Olduvai IV: Courage
Click on image to read excerpts

Olduvai II: Exodus
Click on image to purchase

Click on image to purchase @ FriesenPress